




|
| Raw
Materials |
|
|
Sand, gravel,
and cement are transported to the concrete plant by truck. Certain
materials, such as inert aggregates, are typically stored outdoors
in stockpiles. Moisture-sensitive materials, such as cement and flyash,
may be stored in high-capacity silos. |
| Batching
+ Mixing |
|
|
As the materials
are needed, they are transported by conveyor to large storage bins
at the top of the block plant. At the start of production, the raw
materials are discharged into a weigh batcher, which measures the
correct proportion of dry materials for the mix. The dry materials
are mixed for several minutes before water and admixtures are added.
The proportioning of the mix is carefully controlled by computer.
Most concrete block is produced using zero-slump concrete, which requires
a minimal amount of water. |
| Molding
+ Curing |
|
|
After mixing is
complete, the batch is discharged into a hopper and compacted into
molds. Each mold consists of a re-usable, one-piece mold box with
replaceable liners. The molds are compacted using pressure and vibration
to assure an even distribution of concrete. The compacted block is
pressed out of the mold onto a moving conveyor belt. As the block
travels down the belt, a rotating brush removes loose particles of
aggregate from the top surface of the block. At this stage of the
process, the uncured blocks as referred to as "green." The "green"
blocks are mechanically loaded onto a curing rack. Fully-loaded curing
racks are then transported by forklift into an available steam-curing
kiln. Racks of concrete block are placed in the steam-curing kiln
at normal temperature for a holding period of 1-3 hours. This "presetting"
allows the blocks to harden slightly. Steam is then gradually introduced,
increasing the kiln temperature incrementally, until peak temperature
(usually 165-170 degrees) is reached. The blocks are then allowed
to "soak" in the steam for 12-18 hours. Finally, the moist air is
exhausted to allow the blocks to dry. |
| Storage
+ Transport |
|
|
Pallets of cured
block are then removed from the kiln and transported by forklift to
outdoor storage yards. Steam-cured block typically reaches 90% of
its final strength within 2 to 4 days. Large quantities of standard-sized
blocks are stored until ready for transport to the jobsite. Blocks
are transported by flat-bed truck to the jobsite. |
slide
show
main |
|